    * Agreement executed with Contractor – Package No. TSR-WS-01.
    * Accepted amount is Rs. 42,18,18,118/-
    * Joint Account opened with Superintending Engineer, KWA & Secretary, Thrissur Corporation.
    * Total payment released to the Contractor Rs. 8,21,52,196/-(including mobilization advance Rs. 4,21,81,812/- )
    * 14.78 km of 700 mm DI pipe collected at site.
    * 9.45 km pipe laying completed.

SWM

SOLID WASTE MANAGEMENT
Chronology of events for SWM works

    * Agreement Signed on 06.03.08.
    * Contract Period 18 months.
    * Contract Amount Rs. 4, 92, 39,711/-.
    * Completion date 05.09.09.
    * Completion date extended upto 31-12-09
    * Financial Progress till date Rs.17,48,378/-(3.55%).

PROGRESS OF SWM WORKS

Roads

URT WORKS

PSF

PSF ACTIVITIES

    * Advanced DTP, Computerized Financial Accounting & 3,4 wheeler Driving training completed and distributed the certificates.
    * Financial assistance released to ICE Queen & Bake, Malayalam Bakery, Sopanam Photostat, Stitching world and canteen unit at Vydhudhi Bhavanam and Sastha Pappadom - Micro enterprise groups.
    * Kitchen & dining hall for Anappara Orphanage construction completed.