Water Supply

    * Agreement executed with Contractor – Package No. TSR-WS-01.
    * Accepted amount is Rs. 42,18,18,118/-
    * Joint Account opened with Superintending Engineer, KWA & Secretary, Thrissur Corporation.
    * Total payment released to the Contractor Rs. 8,21,52,196/-(including mobilization advance Rs. 4,21,81,812/- )
    * 14.78 km of 700 mm DI pipe collected at site.
    * 9.45 km pipe laying completed.